| Preface | 7 |
|---|
| Introduction | 12 |
|---|
| Contents | 15 |
|---|
| List of Acronyms | 18 |
|---|
| List of Figures | 22 |
|---|
| List of Tables | 25 |
|---|
| Chapter 1 The EVM Fundamentals | 27 |
|---|
| 1.1 Earned Value Management (EVM) | 28 |
| 1.1.1 The metrics | 28 |
| 1.1.2 Performance measures | 31 |
| 1.1.3 Forecasting formula | 35 |
| 1.2 A fictitious project example | 44 |
| 1.3 Conclusion | 47 |
| Chapter 2 Beyond the EVM Fundamentals | 51 |
|---|
| 2.1 The p-factor concept for schedule adherence | 52 |
| 2.1.1 Activity overlapping | 55 |
| 2.1.2 EV/PV accrue deviation | 55 |
| 2.1.3 Ahead or delays in activities | 56 |
| 2.2 Rework due to lack of schedule adherence | 56 |
| 2.3 Conclusion | 60 |
| Chapter 3 A Case Study | 62 |
|---|
| 3.1 Project 1. Revamp check-in | 65 |
| 3.2 Project 2. Link lines | 68 |
| 3.3 Project 3. Transfer platform | 68 |
| 3.4 Conclusion | 72 |
| Chapter 4 A Simulation Study | 75 |
|---|
| 4.1 Test methodology | 77 |
| 4.1.1 The project generation | 78 |
| 4.1.2 Project data | 86 |
| 4.2 Simulation 1: A forecast accuracy study | 87 |
| 4.2.1 Simulation model | 87 |
| 4.2.2 The forecast accuracy under 9 scenarios | 91 |
| 4.2.3 The forecast accuracy and the completion stage of work | 94 |
| 4.2.4 The influence of the network structure on the forecast accuracy | 97 |
| 4.3 Simulation 2: A schedule adherence study | 102 |
| 4.3.1 Simulation model | 102 |
| 4.3.2 The p-factor evolution and topological structure | 104 |
| 4.3.3 The p-factor and the duration forecasting accuracy | 106 |
| 4.3.4 The effective forecasting accuracy | 108 |
| 4.4 Conclusion | 109 |
| Chapter 5 Time Sensitivity | 111 |
|---|
| 5.1 Introduction | 111 |
| 5.2 Literature overview | 112 |
| 5.2.1 Activity-based sensitivity measures | 112 |
| 5.2.2 An illustrative example | 115 |
| 5.2.3 A critical view on sensitivity measures | 119 |
| 5.3 Simulation 3: An activity sensitivity study | 121 |
| 5.3.1 Test design | 122 |
| 5.3.2 Corrective actions | 122 |
| 5.3.3 Action threshold = average sensitivity value | 124 |
| 5.3.4 Action threshold = xth percentile sensitivity value | 125 |
| 5.4 Conclusion | 128 |
| Chapter 6 Top-down or Bottom-up Project Tracking | 130 |
|---|
| 6.1 Introduction | 130 |
| 6.2 Project scheduling and monitoring | 131 |
| 6.3 Simulation 4: A top-down/bottom-up tracking study | 133 |
| 6.3.1 Simulation model | 133 |
| 6.3.2 Effect of the project structure | 136 |
| 6.3.3 Effect of time uncertainty | 137 |
| 6.3.4 Effect of action threshold | 139 |
| 6.4 Conclusion | 141 |
| Chapter 7 ProTrack: A Software Tutorial | 143 |
|---|
| 7.1 Project scheduling with ProTrack | 143 |
| 7.1.1 Precedence relations | 144 |
| 7.1.2 Activity constraints | 144 |
| 7.1.3 Earliest/Latest start schedule | 147 |
| 7.1.4 Baseline schedule | 149 |
| 7.2 Tracking progress with ProTrack | 149 |
| 7.2.1 Earned value/earned schedule | 151 |
| 7.2.2 Retained or overridden logic | 153 |
| 7.2.3 Project reports | 155 |
| 7.3 ProTrack engines | 155 |
| 7.3.1 Project generation engine | 156 |
| 7.3.2 Simulation engine | 156 |
| 7.3.3 Time forecasting engine | 158 |
| 7.4 Demo experiment | 160 |
| 7.4.1 Determinants of forecast accuracy | 161 |
| 7.4.2 ProTrack simulation experiment | 165 |
| 7.5 Conclusion | 168 |
| Chapter 8 Conclusions | 170 |
|---|
| 8.1 Forecast accuracy | 171 |
| 8.2 Schedule adherence | 172 |
| 8.3 Time sensitivity | 173 |
| 8.4 Summary | 174 |
| References | 177 |
|---|
| Index | 183 |