: Mario Vanhoucke
: Measuring Time Improving Project Performance Using Earned Value Management
: Springer-Verlag
: 9781441910141
: 1
: CHF 85.90
:
: Allgemeines, Lexika
: English
: 164
: Wasserzeichen
: PC/MAC/eReader/Tablet
: PDF

Meant to complement rather than compete with the existing books on the subject, this book deals with the project performance and control phases of the project life cycle to present a detailed investigation of the project's time performance measurement methods and risk analysis techniques in order to evaluate existing and newly developed methods in terms of their abilities to improve the corrective actions decision-making process during project tracking. As readers apply what is learned from the book, EVM practices will become even more effective in project management and cost engineering. Individual chapters look at simulation studies in forecast accuracy; schedule adherence; time sensitivity; activity sensitivity; and using top-down or bottom-up project tracking. Vanhoucke also offers an actual real-life case study, a tutorial on the use of ProTrack software (newly developed based on his research) in EVM, and conclusions on the relative effectiveness for each technique presented.



Prof Dr Mario Vanhouckeis associate professor at Ghent University and Vlerick Leuven Gent Management School (Belgium). He teaches Project Management, Business Statistics and Applied Operations Research. He is program director of the Bachelors and Masters in Business Engineering and the advanced Master in Operations and Technology Management and is a partner of OR-AS. His main research interest lies in simulation and optimization models in project scheduling and scheduling in the health care sector. This November he was awarded the 2008 International Project Management Association Research Award for the research project upon which this proposed book is based -(http://www.ipma.ch/awards/r sawards/Pages/winnersandhonou s2008.aspx).

 

Preface7
Introduction12
Contents15
List of Acronyms18
List of Figures22
List of Tables25
Chapter 1 The EVM Fundamentals27
1.1 Earned Value Management (EVM)28
1.1.1 The metrics28
1.1.2 Performance measures31
1.1.3 Forecasting formula35
1.2 A fictitious project example44
1.3 Conclusion47
Chapter 2 Beyond the EVM Fundamentals51
2.1 The p-factor concept for schedule adherence52
2.1.1 Activity overlapping55
2.1.2 EV/PV accrue deviation55
2.1.3 Ahead or delays in activities56
2.2 Rework due to lack of schedule adherence56
2.3 Conclusion60
Chapter 3 A Case Study62
3.1 Project 1. Revamp check-in65
3.2 Project 2. Link lines68
3.3 Project 3. Transfer platform68
3.4 Conclusion72
Chapter 4 A Simulation Study75
4.1 Test methodology77
4.1.1 The project generation78
4.1.2 Project data86
4.2 Simulation 1: A forecast accuracy study87
4.2.1 Simulation model87
4.2.2 The forecast accuracy under 9 scenarios91
4.2.3 The forecast accuracy and the completion stage of work94
4.2.4 The influence of the network structure on the forecast accuracy97
4.3 Simulation 2: A schedule adherence study102
4.3.1 Simulation model102
4.3.2 The p-factor evolution and topological structure104
4.3.3 The p-factor and the duration forecasting accuracy106
4.3.4 The effective forecasting accuracy108
4.4 Conclusion109
Chapter 5 Time Sensitivity111
5.1 Introduction111
5.2 Literature overview112
5.2.1 Activity-based sensitivity measures112
5.2.2 An illustrative example115
5.2.3 A critical view on sensitivity measures119
5.3 Simulation 3: An activity sensitivity study121
5.3.1 Test design122
5.3.2 Corrective actions122
5.3.3 Action threshold = average sensitivity value124
5.3.4 Action threshold = xth percentile sensitivity value125
5.4 Conclusion128
Chapter 6 Top-down or Bottom-up Project Tracking130
6.1 Introduction130
6.2 Project scheduling and monitoring131
6.3 Simulation 4: A top-down/bottom-up tracking study133
6.3.1 Simulation model133
6.3.2 Effect of the project structure136
6.3.3 Effect of time uncertainty137
6.3.4 Effect of action threshold139
6.4 Conclusion141
Chapter 7 ProTrack: A Software Tutorial143
7.1 Project scheduling with ProTrack143
7.1.1 Precedence relations144
7.1.2 Activity constraints144
7.1.3 Earliest/Latest start schedule147
7.1.4 Baseline schedule149
7.2 Tracking progress with ProTrack149
7.2.1 Earned value/earned schedule151
7.2.2 Retained or overridden logic153
7.2.3 Project reports155
7.3 ProTrack engines155
7.3.1 Project generation engine156
7.3.2 Simulation engine156
7.3.3 Time forecasting engine158
7.4 Demo experiment160
7.4.1 Determinants of forecast accuracy161
7.4.2 ProTrack simulation experiment165
7.5 Conclusion168
Chapter 8 Conclusions170
8.1 Forecast accuracy171
8.2 Schedule adherence172
8.3 Time sensitivity173
8.4 Summary174
References177
Index183